Welcome to the Davenport Recycled Water Project!


The Davenport Recycled Water Project (DRWP) is a project to upgrade the existing wastewater treatment plant in Davenport. This project will upgrade the Davenport County Sanitation District’s wastewater treatment plant by dredging accumulated solids in the treatment lagoon, installing alarms for the filtration and disinfection processes, and adding redundancy for coagulant and hypochlorite dosing. The project also consists of the construction of a storage pond for treated water, which will allow adjacent farmers to use recycled water for irrigation.


Monday, October 22, 2018

October Update

https://www.santacruzsentinel.com/2018/10/18/davenport-launches-new-coastal-recycled-water-project/

The ribbon cutting for the recycled water treatment plant on 10/18/2018

 
 
 The community watched as the completed storage pond filled up with recycled water. 

 
 
The recycled water storage tank and truck fill station that will soon be available to the public once the State required Title 22 process for regulating the recycled water is finalized.

 
Stay tuned to learn more about purchasing recycled water.

Thursday, September 27, 2018

September Update

The Davenport Recycled Water Project will be completed in the next week.  The landscaping around the pond has been completed.  Currently construction crews are working to complete the treatment plant’s instrumentation and controls and putting the finishing touches on the truck fill station.  A successful test of the system pumped tertiary treated water to the holding pond.  

Pond Landscaping

Truck Fill Station

Friday, August 17, 2018

August Update

The Davenport Recycled Water Project is nearing completion.  Since the last post, the following work has been performed:
  1. The recycled water storage pond has been excavated and lined.
  2. The recycled water line has been installed under Highway 1 and is a possible future source for irrigation for the farming on the State Parks Property.
  3. The recycled water line has been installed in Cement Plant Road between the treatment plant and the storage pond. 
  4. Work has progressed at the truck fill station where the public will be able to purchase recycled water for approved uses.
The landscaping around the pond will be installed in the next couple of weeks.  Contractors will continue their work installing instrumentation for the treatment plant.  The project is scheduled to be completed in mid to late September.

Tuesday, June 12, 2018

June Update


The construction of the recycled water force main in Cement Plant road is progressing.  Construction crews uncovered multiple unexpected underground utilities and obstacles during construction of the force main, causing delays.  We appreciate your continued patience during this period of traffic detours.

This week construction crews will be beginning the jack and bore operation under the railroad tracks and Highway 1.  This work will provide the farmer on the ocean-side of Highway 1 with the ability to irrigate the farmland with recycled water from the treatment plant in the future.

Also beginning this week is grading work for the recycle water storage pond located on the property along Warnella Road.  The recycled water in the storage pond will be used by the property owner for irrigation and will be available for the general public to purchase at the recycled water fill station.  Purchasers of the recycled water must pre-register with the Davenport County Sanitation District and agree to only use the recycled water for approved uses.

Wednesday, April 25, 2018

April 25th Update

Dredging of the wastewater treatment lagoon was completed in mid-December.  Upgrades to the recycled water treatment plant are nearly complete.  Construction of the waterline along Cement Plant Road (extending from the treatment plant to the storage pond on the farmland property) will begin soon.  In preparation, construction crews will be potholing the road in the next couple of weeks.  Traffic will be diverted around the construction crews as needed during this time.  Over the next two months as the waterline is constructed, detours will route traffic around the closed portion of Cement Plant Road via Highway 1 and via Adeline Street.  The detour will be in place from around 8:00 am to 5 p.m.  Mondays through Fridays.

Friday, December 1, 2017

December Update


Dredging of the wastewater treatment lagoon started on November 30th. The dredge (red piece of equipment in the pond shown in the picture) cuts and “vacuums” up accumulated sludge from the bottom of the pond and sends it to a holding tank. The sludge then goes through a grinder, after which a polymer is added before it enters a centrifuge where liquid is taken out. The dried sludge is loaded into trucks (it takes about 4 hours to fill one truck) and the liquid is returned to the pond. The dredging process is expected to take 3-4 weeks.